TANK CUTTING PROPOSAL
WATERJET TANK CUTTING WAYCO ENVIRONMENTAL
The scope includes cutting two steel tanks into sections for dismantling. Each tank will receive two intersecting top cuts, four vertical sidewall cuts, and a continuous horizontal cut around the lower perimeter. The cutting sequence is intended to allow the separated sections to fall inward and remain within the tank footprint.
Compliant








01 — PROJECT AREA + SCOPE
DEVON RESEARCH CENTRE
Wayco Environmental
CANMET ENERGY - NATURAL RESOURCES CANADA
The proposed cutting sequence will be completed on each tank as follows:
- Top section: Complete two intersecting cuts across the tank top at right angles, dividing it into four quarter sections.
- Tank walls: Complete four vertical cuts down the tank sidewall, extending to the designated lower cut elevation.
- Lower perimeter: Complete a continuous horizontal cut around the tank circumference at the base of the vertical cuts, separating the sidewall sections from the remaining tank base.
The intended outcome is for the separated top and sidewall sections to fall inward and remain within the tank footprint. Final cut locations, sequencing, and measures to control section movement will be confirmed before work begins.
02 — Rates
Equipment & Rate Schedule
Itemized project estimate showing the supplied units, quantities, rates and extended totals.
Cutting Operations
Cut Truck Mobilization
Minutes × 045 at $0.00$425.00
$0.00$318.75
Cut Truck Demobilization
Minutes × 045 at $0.00$425.00
$0.00$318.75
Cutting Truck - Onsite Day #1
Hourly × 010 at $0.00$550.00
$0.00$5,500.00
Cutting Truck - Onsite Day #2
Hourly × 010 at $0.00$550.00
$0.00$5,500.00
Crew & Logistics
Supervisor
Hourly × 016 at $0.00$120.00
$0.00$1,920.00
Operator
Hourly × 016 at $0.00$100.00
$0.00$1,600.00
Labourer
Hourly × 016 at $0.00$80.00
$0.00$1,280.00
Support Truck Hourly
Hourly × 016 at $0.00$25.00
$0.00$400.00
Support Truck Milage
KMs × 0108 at $0.00$2.00
$0.00$216.00
Estimated Project Total
Based on the units and quantities listed above.
$0.00$17,053.50
03 — Contacts
Contacts & Next Steps
Leads on both sides of the project, and what has to close before the crew mobilizes.

Wayco Environmental
Address
1409 – 4th Street,Nisku, AB T9E 7M9
Innovative Well Abandonment
Address
11630 Kingsway NW,Edmonton, Albert T5G 0X5